Wage determination OR20260064, modification 1
Effective May 18, 2026. Covers 1 Oregon county for Heavy work, with 35 rate lines. Base rates run $17.22–$64.17 and fringe $2.96–$34.52 across the classifications listed.
What this determination covers
This is a federal Davis-Bacon determination published on SAM.gov. It applies to federally funded or assisted construction in the counties listed below, for the construction types shown. State-funded public works in Oregon are governed by the state's own schedule, which is a separate set of rates — see Oregon rates.
The contract controls: if the contract names this determination with a different modification, that version governs, even when a newer determination exists. Copy the number and the modification into field 5 of the WH-347.
| Attribute | Value |
|---|---|
| Determination | OR20260064 |
| Modification | 1 |
| Effective | May 18, 2026 |
| Construction types | Heavy |
| Counties | 1 |
| Rate lines | 35 |
| Other Oregon determinations | 74 active in this state → |
Rate table
Every classification the determination lists, with the basic hourly rate, the fringe rate and the total package. Overtime is 1.5× the basic hourly rate; fringe is not multiplied. A row marked per day is a daily rate rather than an hourly one.
| Classification | Base rate | Fringe | Total | Effective | Code |
|---|---|---|---|---|---|
| Millwright | $59.35 | $22.38 | $81.73 | 06/01/2025 | CARP0096-006 |
| Carpenter | $53.94 | $16.81 | $70.75 | 06/01/2025 | CARP0503-018 |
| Line Construction | $64.17 | $24.54 | $88.71 | 02/01/2024 | ELEC0125-002 |
| Electrician | $50.03 | $24.00 | $74.03 | 01/01/2024 | ELEC0932-012 |
| Power Equipment Operator | $45.81 | $16.90 | $62.71 | 01/01/2024 | ENGI0701-036 |
| Power Equipment Operator | $49.03 | $16.90 | $65.93 | 01/01/2024 | ENGI0701-036 |
| Power Equipment Operator | $50.27 | $16.90 | $67.17 | 01/01/2024 | ENGI0701-036 |
| Power Equipment Operator | $53.60 | $16.90 | $70.50 | 01/01/2024 | ENGI0701-036 |
| Power Equipment Operator | $54.75 | $16.90 | $71.65 | 01/01/2024 | ENGI0701-036 |
| Power Equipment Operator | $60.98 | $16.90 | $77.88 | 01/01/2024 | ENGI0701-036 |
| Power Equipment Operator | $58.82 | $16.90 | $75.72 | 01/01/2024 | ENGI0701-036 |
| Power Equipment Operator | $56.66 | $16.90 | $73.56 | 01/01/2024 | ENGI0701-036 |
| Power Equipment Operator | $49.03 | $16.90 | $65.93 | 01/01/2024 | ENGI0701-037 |
| Power Equipment Operator | $50.27 | $16.90 | $67.17 | 01/01/2024 | ENGI0701-037 |
| Power Equipment Operator | $53.60 | $16.90 | $70.50 | 01/01/2024 | ENGI0701-037 |
| Power Equipment Operator | $54.75 | $16.90 | $71.65 | 01/01/2024 | ENGI0701-037 |
| Ironworker | $48.31 | $34.52 | $82.83 | 07/07/2025 | IRON0029-013 |
| Laborers | $40.41 | $17.30 | $57.71 | 06/01/2024 | LABO0737-032 |
| Laborers | $39.11 | $17.30 | $56.41 | 06/01/2024 | LABO0737-032 |
| Painters | $39.94 | $16.68 | $56.62 | 07/01/2025 | PAIN0010-006 |
| Cement Mason/concrete Finisher | $46.13 | $20.31 | $66.44 | 06/01/2025 | PLAS0555-006 |
| Truck Driver | $31.81 | $6.33 | $38.14 | 11/23/2009 | SUOR2009-062 |
| Truck Driver | $17.22 | $4.83 | $22.05 | 11/23/2009 | SUOR2009-062 |
| Operator | $27.59 | $2.96 | $30.55 | 11/23/2009 | SUOR2009-062 |
| Operator | $20.64 | $5.58 | $26.22 | 11/23/2009 | SUOR2009-062 |
| Operator | $21.73 | $6.32 | $28.05 | 11/23/2009 | SUOR2009-062 |
| Operator | $32.31 | $6.43 | $38.74 | 11/23/2009 | SUOR2009-062 |
| Operator | $22.77 | $7.90 | $30.67 | 11/23/2009 | SUOR2009-062 |
| Laborer | $20.77 | $6.51 | $27.28 | 11/23/2009 | SUOR2009-062 |
| Laborer | $21.27 | $5.35 | $26.62 | 11/23/2009 | SUOR2009-062 |
| Laborer | $18.76 | $6.15 | $24.91 | 11/23/2009 | SUOR2009-062 |
| Truck Driver | $36.08 | $18.30 | $54.38 | 06/01/2025 | TEAM0037-012 |
| Truck Driver | $35.74 | $18.30 | $54.04 | 06/01/2025 | TEAM0037-012 |
| Truck Driver | $35.57 | $18.30 | $53.87 | 06/01/2025 | TEAM0037-012 |
| Truck Driver | $35.41 | $18.30 | $53.71 | 06/01/2025 | TEAM0037-012 |
Counties covered
Each link opens the county lookup already set to this county and this determination.
Using it on a payroll
- Confirm the version. Take the modification from the contract, not from this page — this page shows the newest published modification.
- Match the classification, not the job title. A title the determination does not list is a rejection even at a higher rate.
- Split base and fringe. Show the basic rate in 6A, the plan credit in 6B and cash in lieu in 6C; omitting fringe is a shortfall, not a saving.
- Check the overtime clock. This state uses a forty-hour workweek test.
The field-by-field mapping is in the WH-347 guide.